Dongfang 600 MW supercritical boiler has reached the international advanced level
basalt fiber,basalt cloth,basalt fiber cloth Chongqing Qingtao Fiberglass Products Co., Ltd. , https://www.eifsfiberglassmesh.com
In 1999, the former State Planning Commission determined that Yubei Power Plant was the technology introduction and localization support project for China's 600 MW supercritical unit. In May 2002, Dongguo and Huaneng Yubei Power Plant officially signed the supply contract for the 2×600 MW supercritical boiler equipment in Weibei, and signed a national major technical equipment development project “600 MW supercritical†with the Machinery Industry Federation. Four special contracts in the development of thermal power unit equipment. With its own strength, Dongpan completed the design and manufacture of the first domestic 600 MW supercritical unit boiler with a localization rate of 100% in 23 months under the technical support of Japan BHK. At the end of 2004, the two units of boilers passed the 168-hour trial run and officially put into commercial operation with excellent quality. After nearly two years of operation and performance test, the main performance indicators of the 600 MW supercritical unit in Weibei are excellent. Guaranteed value for design.
After the success of the 600 MW supercritical boiler project of Yubei Power Plant, in May 2006, Dongfang’s four topics of “600 MW supercritical thermal power unit equipment development†successfully passed the acceptance of the results of the national organization, which marked Dongpan has made significant progress in high-efficiency, low-consumption, environmentally-friendly large-capacity, high-parameter boiler design and manufacturing technology, providing a strong guarantee for the sustainable and stable development of the company.